Freedom Road construction update

The reconstruction of Freedom Road from Maple Avenue to west of Tree Hill Boulevard began May 27 and will continue through August 28, weather permitting. Due to the encounter of unforeseen and deteriorating existing concrete conditions found during the removal of the asphalt surface, the project team will reduce the traffic use of Freedom Road within the project limits to local traffic (residents and businesses) only.

Access to homes and businesses will remain available along Freedom Road, but thru traffic along Freedom Road must detour. Motorists should seek an alternate route using either 9 Mile Road or Grand River Avenue.

In the Farmington Hills jurisdiction, two-way traffic for residents to their homes will remain in place from Hillview Court to Gill Rd.

 

 

 